quaex

Parth Asset Management System - GitHub Projects Roadmap

Overview

This document outlines the complete development plan for transforming Parth from a prototype into a production-ready enterprise asset management system. The plan is structured into epics, milestones, and specific tasks suitable for GitHub Projects implementation.

Project Structure

Epic 1: Foundation & Security 🔐

Timeline: 2-3 weeks
Priority: Critical
Status: 70% Complete

Milestone 1.1: Authentication & Security Hardening

Milestone 1.2: Core Infrastructure

Epic 2: Asset Management Core 📦

Timeline: 4-6 weeks
Priority: High
Status: 0% Complete

Milestone 2.1: Asset Data Models

Milestone 2.2: Asset CRUD Operations

Milestone 2.3: Location Management

Epic 3: Inventory Management 📊

Timeline: 3-4 weeks
Priority: High
Status: 0% Complete

Milestone 3.1: Stock Tracking

Milestone 3.2: Inventory Operations

Epic 4: Mobile & QR/Barcode Features 📱

Timeline: 2-3 weeks
Priority: High
Status: 0% Complete

Milestone 4.1: QR/Barcode Implementation

Milestone 4.2: Mobile-Optimized Workflows

Epic 5: User Management & Permissions 👥

Timeline: 2-3 weeks
Priority: Medium
Status: 10% Complete

Milestone 5.1: User Roles & Permissions

Milestone 5.2: Team Collaboration

Epic 6: Maintenance & Work Orders 🔧

Timeline: 3-4 weeks
Priority: Medium
Status: 0% Complete

Milestone 6.1: Preventive Maintenance

Milestone 6.2: Work Order System

Epic 7: Reporting & Analytics 📈

Timeline: 2-3 weeks
Priority: Medium
Status: 0% Complete

Milestone 7.1: Standard Reports

Milestone 7.2: Business Intelligence

Epic 8: Integration & API 🔌

Timeline: 2-3 weeks
Priority: Low-Medium
Status: 0% Complete

Milestone 8.1: API Development

Milestone 8.2: External Integrations

Epic 9: Performance & Scalability ⚡

Timeline: 2-3 weeks
Priority: Medium
Status: 0% Complete

Milestone 9.1: Performance Optimization

Milestone 9.2: Scalability Preparation

Epic 10: Production Readiness & Launch 🚀

Timeline: 2-3 weeks
Priority: Critical
Status: 20% Complete

Milestone 10.1: Production Infrastructure

Milestone 10.2: Quality Assurance

Milestone 10.3: Documentation & Training

Milestone 10.4: Launch Preparation

Implementation Timeline

Phase 1 (Weeks 1-4): Foundation

Phase 2 (Weeks 5-10): Core Features

Phase 3 (Weeks 11-16): Advanced Features

Phase 4 (Weeks 17-22): Business Intelligence & Integration

Phase 5 (Weeks 23-26): Production Launch

Success Metrics

Technical Metrics

Business Metrics

Resource Requirements

Development Team

Infrastructure

Risk Mitigation

Technical Risks

Business Risks

Next Steps

  1. Create GitHub Project: Set up the project board with these epics and milestones
  2. Epic 1 Completion: Finish remaining security and infrastructure tasks
  3. Epic 2 Kickoff: Begin asset management core development
  4. Team Onboarding: Recruit and onboard additional team members as needed
  5. User Research: Begin gathering feedback from potential enterprise users

Last Updated: September 25, 2025
Version: 1.0
Owner: Parth Development Team